Close Menu
  • O NAMA
  • KONTAKT
  • UVJETI KORIšTENJA
  • NASLOVNICA
  • VIJESTI
    • Hrvatska
    • Svijet
    • Politika
    • Crna kronika
    • Novosti iz regije
  • BUSINESS
  • SPORT
    • Nogomet
    • Košarka
    • Tenis
    • Rukomet
    • F-1 i auto-moto
    • Fight
    • Ostali sportovi
  • ZABAVA
    • Lifestyle
    • Turizam i putovanja
    • Zdravlje i hrana
    • Kućni ljubimci
  • CELEBRITY/ INFL
  • FILM / GLAZBA
  • AUTO MOTO
    • Auto-moto vijesti
    • Testovi
    • Motocikli
    • Tuning & styling & servis
    • Oldtimeri
  • TECH
Facebook X (Twitter) Instagram Threads
Facebook X (Twitter) Instagram
times-news.eu
Pretplatite se
  • NASLOVNICA
  • VIJESTI
    • Hrvatska
    • Svijet
    • Politika
    • Crna kronika
    • Novosti iz regije
  • BUSINESS
  • SPORT
    • Nogomet
    • Košarka
    • Tenis
    • Rukomet
    • F-1 i auto-moto
    • Fight
    • Ostali sportovi
  • ZABAVA
    • Lifestyle
    • Turizam i putovanja
    • Zdravlje i hrana
    • Kućni ljubimci
  • CELEBRITY/ INFL
  • FILM / GLAZBA
  • AUTO MOTO
    • Auto-moto vijesti
    • Testovi
    • Motocikli
    • Tuning & styling & servis
    • Oldtimeri
  • TECH
times-news.eu
You are at:Home»Politika»HS2 already billions over budget with work ‘just over halfway done’, says rail boss | HS2
Politika

HS2 already billions over budget with work ‘just over halfway done’, says rail boss | HS2

July 9, 2025No Comments3 Mins Read0 Views
Share

HS2 construction contracts priced at £19.5bn have already cost £26bn despite being “just over halfway done”, the boss of the high-speed rail project has told MPs.

Civil engineering to build tunnels and cuttings for the 100-mile line should be almost finished but is closer to 60% complete, while only a third of the wider project – including laying tracks and wiring – is done, the transport select committee heard on Wednesday.

Mark Wild, chief executive of HS2 Ltd, told the committee that the rush to start work in 2020 without balancing the risks in the contracts was the major reason for costs spiralling upwards.

Contracts were signed off in April 2020 and construction formally began five months later, before designs were finalised and local planning consents were in place, he said.

Wild, who started work last December, is currently engaged in a “reset” of construction, which he said would include reshaping his direct staff at HS2 Ltd, coming up with a credible schedule and budget, and renegotiating contracts in the autumn.

He said: “The bottom line is that, at the notice to proceed, the contractors could not price the risk. What we’re seeing is the crystallisation of risk: they should have cost £19.5bn, and we’ve already spent £26bn and we’re just over halfway done … Between 50% and 100% is the likely overspend.”

The line between London and Birmingham – initially designated phase one, but now the entirety of HS2 – was originally planned to open in 2026.

The schedule was subsequently postponed to between 2029 and 2033. But on Wild’s advice, Heidi Alexander, the transport secretary, told parliament last month that there was “no route” to full HS2 services until after 2033.

Wild said Covid and inflation caused by Russia’s invasion of Ukraine had both had significant impact on time and costs, but that HS2 had failed to manage costs.

He said the company was “unbalanced” and had “a significant gap” in its frontline workforce managing contractors, as well as having “too many consultants who’ve been there for too long”.

“We’ve ended up … locked in our own bureaucracy,” he added.

Also giving evidence, Lord Hendy said politicians had to be ultimately accountable for the decisions made. The rail minister told the committee it was unclear why political leaders had decided HS2 should be an “exceptionally fast railway”.

skip past newsletter promotion

Sign up to Business Today

Get set for the working day – we’ll point you to all the business news and analysis you need every morning

Privacy Notice: Newsletters may contain info about charities, online ads, and content funded by outside parties. For more information see our Privacy Policy. We use Google reCaptcha to protect our website and the Google Privacy Policy and Terms of Service apply.

after newsletter promotion

While accepting that higher speed did increase potential capacity, he added: “It is hard to understand why there was such zealotry about the highest-speed railway in a relatively small country.”

HS2 trains will have a maximum speed of 225 miles per hour, though Wild suggested last month they start running at lower speeds to reduce the period needed for testing and potentially run services sooner.

Wild told the committee he was confident that HS2 could “get a reset” in partnership with contractors who “are working across government and are part of a much bigger game than just HS2”.

With major contracts to be awarded on work such as the Sizewell C nuclear plant and upgrading the National Grid, Hendy said he believed firms would “lean in” to Wild’s plans.

Share. Facebook Twitter WhatsApp Telegram
Previous ArticleSlobodna Dalmacija – Drama u Zagrebu, vatrogasci u zadnji čas spasili mladi par: ‘Za sve je kriv taj čovjek, smetlište mu je ispred stana!’
Next Article Ukraine suffers heaviest attack as Trump criticises Putin

Related Posts

Hrvatski stočari najavili prosvjede u Vukovaru: Ministru Vlajčiću poručeno “Radite ili dajte ostavku!”

August 22, 2025

U Hrvatskoj se razmatra obveza poznavanja jezika za strane radnike

August 20, 2025

EU i Francuska snažno osudile izraelsko rušenje škole u izgradnji na Zapadnoj obali

August 20, 2025
Leave A Reply Cancel Reply

Recent Posts
  • Europolova Operacija ‘DECOY II’ Zaustavila Krivotvoritelje Valute: Hrvatska Među 18 Zemalja Sudionica
  • Hrvatske plaće nadmašile češke, ali raste zabrinutost za tržište rada
  • Mješovita kretanja dionica Končar Grupe na Zagrebačkoj burzi unatoč blagom rastu indeksa
  • Hrvatska inflacija nastavlja rasti treći mjesec zaredom, svrstana među najviše stope u Eurozoni
  • Izrada vijesti nije moguća: Izvorni materijal nije priložen
  • Facebook
  • Twitter
  • Instagram
  • YouTube
  • TikTok
Facebook X (Twitter) Instagram TikTok

Europolova Operacija ‘DECOY II’ Zaustavila Krivotvoritelje Valute: Hrvatska Među 18 Zemalja Sudionica

Hrvatske plaće nadmašile češke, ali raste zabrinutost za tržište rada

Mješovita kretanja dionica Končar Grupe na Zagrebačkoj burzi unatoč blagom rastu indeksa

Neuspjeh u dohvaćanju vijesti: Tehničke poteškoće spriječile potvrdu objave

Valamar donosi ESPA: Prvi luksuzni wellness centar svjetski poznatog brenda otvara se u Istri

Alat za pregledavanje naišao na tehničku prepreku u prikupljanju podataka

  • O NAMA
  • KONTAKT
  • UVJETI KORIšTENJA

Type above and press Enter to search. Press Esc to cancel.